Four laning of Phagwara to Rupnagar section of NH-344A from km. 0.00 (design chainage) to km. 80.820 (design chainage).
| SPV | GR Phagwara Expressway Limited (GPEL) |
|---|---|
| Authority | National Highways Authority of India (NHAI) |
| Project Location | Punjab |
| Appointed Date | 6th October 2017 |
| Construction Period | 910 Days |
| PCOD | 25th Feb 2020 |
| COD | 26th May 2021 |